ProofNotFluff

Free Chicago permit tracker

Chicago Permit Wait Times

Chicago issued 31,349 building permits in the 12 months to Nov 1, 2026. Half were issued within 6 days of the City starting review, and 8 in 10 within 42 days. On Standard Plan Review, half took 90 days and 8 in 10 took 179 days.

Standard Plan Review
90 days
half issued within; 8 in 10 within 179
Express Permit Program
3 days
half issued within; 29% the same day
All permits
6 days
half issued within; 8 in 10 within 42
Permits issued
31,349
in the last 12 months

Figures as of Nov 1, 2026: permits issued from Nov 2, 2025 to Nov 1, 2026, from City of Chicago records pulled Nov 2, 2026. Updated weekly.

By permit type

Tap a permit type for its own page with every review path, month and community area.

Permit typePermits issued, 12 monthsHalf within (days)8 in 10 within (days)9 in 10 within (days)Same day
Express Permit Program20,2363122129%
Renovation and Alteration5,305591432110%
Signs2,01638921430%
New Construction1,559551382103%
Elevator Equipment1,12105774%
Wrecking and Demolition659488912132%
Reinstated Revoked Permits45300095%

Wrecking and Demolition: up to February 2026, most of these permits show 0 days in the City's records; from March 2026 on, half took 61 days and 8 in 10 took 104 days (448 permits). Compare months from March 2026 on.

By review path

The review path decides most of the wait. The Express Permit Program is the City's online path for repairs, replacements and small improvements; Standard Plan Review and Self Certification are plan-based paths for projects such as new construction and rehabs (City permit application guide). Days are from the City starting review to the issue date, for permits issued in the last 12 months.

Review pathPermits issued, 12 monthsHalf within (days)8 in 10 within (days)9 in 10 within (days)Same day
Express Permit Program20,2363122129%
Standard Plan Review3,544901792621%
Self Certification2,99532721151%
Signs2,01638921430%
Elevators and Other Conveyances1,12105774%
Wrecking and Demolition659488912132%
Easy Permit45300095%
Direct Developer Services3211132103840%
Traditional Developer Services4too fewtoo fewtoo fewtoo few

Path names are the City's, written out in full.

On a phone the 9 in 10 and same day columns are left out; they are in the CSV below.

Month by month

The last 24 complete months. Pick a review path; each column shows how long the permits issued that month took.

Standard Plan Review, by month issued

Half were issued within (days)8 in 10 were issued within (days)

Self Certification, by month issued

Half were issued within (days)8 in 10 were issued within (days)

Express Permit Program, by month issued

Half were issued within (days)8 in 10 were issued within (days)

Signs, by month issued

Half were issued within (days)8 in 10 were issued within (days)

Every month as a table
Month issuedStandard Plan Review: half / 8 in 10 (days)Self Certification: half / 8 in 10 (days)Express Permit Program: half / 8 in 10 (days)Signs: half / 8 in 10 (days)
Oct 202699 / 188321 permits35 / 81265 permits2 / 121,827 permits32 / 69138 permits
Sep 202672 / 165321 permits31 / 68289 permits4 / 152,124 permits50 / 80204 permits
Aug 202692 / 172337 permits39 / 91281 permits3 / 122,003 permits49 / 116186 permits
Jul 202685 / 180356 permits41 / 83290 permits3 / 131,883 permits49 / 177146 permits
Jun 202687 / 175297 permits33 / 65235 permits3 / 121,949 permits36 / 83212 permits
May 202668 / 163334 permits31 / 64245 permits2 / 91,771 permits25 / 68174 permits
Apr 202676 / 159340 permits30 / 73305 permits2 / 91,767 permits42 / 114237 permits
Mar 2026112 / 211272 permits27 / 70280 permits2 / 91,705 permits28 / 47163 permits
Feb 202695 / 172236 permits32 / 76201 permits3 / 131,243 permits49 / 81108 permits
Jan 2026108 / 189247 permits28 / 69200 permits3 / 151,161 permits33 / 92121 permits
Dec 202597 / 189250 permits27 / 71189 permits5 / 151,255 permits40 / 125152 permits
Nov 202592 / 185233 permits28 / 65215 permits4 / 141,559 permits36 / 112175 permits
Oct 202584 / 167308 permits30 / 76305 permits3 / 132,142 permits32 / 67196 permits
Sep 202577 / 149342 permits34 / 70288 permits2 / 122,014 permits34 / 79147 permits
Aug 202570 / 163339 permits49 / 92243 permits2 / 111,768 permits35 / 110271 permits
Jul 202568 / 156381 permits32 / 63268 permits1 / 91,905 permits30 / 88247 permits
Jun 202571 / 143316 permits40 / 141315 permits3 / 101,850 permits34 / 64260 permits
May 202575 / 171347 permits29 / 85235 permits2 / 81,817 permits35 / 74178 permits
Apr 202564 / 163338 permits30 / 75306 permits2 / 81,852 permits27 / 70305 permits
Mar 202590 / 196252 permits26 / 91253 permits3 / 91,642 permits32 / 85214 permits
Feb 202583 / 189250 permits24 / 69167 permits3 / 121,203 permits29 / 94150 permits
Jan 202572 / 158280 permits27 / 73247 permits5 / 251,420 permits44 / 76164 permits
Dec 202476 / 199237 permits28 / 62231 permits5 / 171,119 permits35 / 80172 permits
Nov 202466 / 175287 permits37 / 78199 permits5 / 141,366 permits33 / 65197 permits

Against a year earlier

Review pathAug to Oct 2026: half within (days)Aug to Oct 2025: half within (days)Change
Standard Plan Review89979 permits77989 permits12 days longer
Self Certification35835 permits36836 permits1 day shorter
Express Permit Program35,954 permits25,924 permits1 day longer
Signs44528 permits35614 permits9 days longer

Wait times on the map

Color the map by
Map of Chicago's 77 community areas, colored by permit wait daysRogers Park: Standard Plan Review: half within 85 daysWest Ridge: Standard Plan Review: half within 84 daysUptown: Standard Plan Review: half within 93 daysLincoln Square: Standard Plan Review: half within 78 daysNorth Center: Standard Plan Review: half within 81 daysLake View: Standard Plan Review: half within 67 daysLincoln Park: Standard Plan Review: half within 88 daysNear North Side: Standard Plan Review: half within 72 daysEdison Park: Standard Plan Review: too few permits to say (18)Norwood Park: Standard Plan Review: half within 73 daysJefferson Park: Standard Plan Review: half within 50 daysForest Glen: Standard Plan Review: half within 79 daysNorth Park: Standard Plan Review: half within 106 daysAlbany Park: Standard Plan Review: half within 103 daysPortage Park: Standard Plan Review: half within 77 daysIrving Park: Standard Plan Review: half within 82 daysDunning: Standard Plan Review: half within 130 daysMontclare: Standard Plan Review: too few permits to say (10)Belmont Cragin: Standard Plan Review: half within 84 daysHermosa: Standard Plan Review: too few permits to say (18)Avondale: Standard Plan Review: half within 135 daysLogan Square: Standard Plan Review: half within 119 daysHumboldt Park: Standard Plan Review: half within 91 daysWest Town: Standard Plan Review: half within 114 daysAustin: Standard Plan Review: half within 103 daysWest Garfield Park: Standard Plan Review: half within 86 daysEast Garfield Park: Standard Plan Review: half within 78 daysNear West Side: Standard Plan Review: half within 54 daysNorth Lawndale: Standard Plan Review: half within 91 daysSouth Lawndale: Standard Plan Review: half within 115 daysLower West Side: Standard Plan Review: half within 101 daysLoop: Standard Plan Review: half within 6 daysNear South Side: Standard Plan Review: half within 19 daysArmour Square: Standard Plan Review: too few permits to say (16)Douglas: Standard Plan Review: too few permits to say (13)Oakland: Standard Plan Review: too few permits to say (3)Fuller Park: Standard Plan Review: too few permits to say (11)Grand Boulevard: Standard Plan Review: half within 106 daysKenwood: Standard Plan Review: half within 106 daysWashington Park: Standard Plan Review: half within 91 daysHyde Park: Standard Plan Review: half within 51 daysWoodlawn: Standard Plan Review: half within 78 daysSouth Shore: Standard Plan Review: half within 89 daysChatham: Standard Plan Review: half within 96 daysAvalon Park: Standard Plan Review: half within 125 daysSouth Chicago: Standard Plan Review: half within 105 daysBurnside: Standard Plan Review: too few permits to say (1)Calumet Heights: Standard Plan Review: too few permits to say (7)Roseland: Standard Plan Review: half within 120 daysPullman: Standard Plan Review: too few permits to say (16)South Deering: Standard Plan Review: too few permits to say (10)East Side: Standard Plan Review: too few permits to say (6)West Pullman: Standard Plan Review: half within 91 daysRiverdale: Standard Plan Review: too few permits to say (4)Hegewisch: Standard Plan Review: too few permits to say (2)Garfield Ridge: Standard Plan Review: half within 60 daysArcher Heights: Standard Plan Review: too few permits to say (13)Brighton Park: Standard Plan Review: half within 98 daysMcKinley Park: Standard Plan Review: half within 118 daysBridgeport: Standard Plan Review: half within 117 daysNew City: Standard Plan Review: half within 121 daysWest Elsdon: Standard Plan Review: too few permits to say (14)Gage Park: Standard Plan Review: too few permits to say (13)Clearing: Standard Plan Review: too few permits to say (9)West Lawn: Standard Plan Review: too few permits to say (12)Chicago Lawn: Standard Plan Review: half within 110 daysWest Englewood: Standard Plan Review: half within 119 daysEnglewood: Standard Plan Review: half within 108 daysGreater Grand Crossing: Standard Plan Review: half within 100 daysAshburn: Standard Plan Review: too few permits to say (17)Auburn Gresham: Standard Plan Review: half within 84 daysBeverly: Standard Plan Review: half within 115 daysWashington Heights: Standard Plan Review: half within 98 daysMount Greenwood: Standard Plan Review: half within 58 daysMorgan Park: Standard Plan Review: half within 97 daysO'Hare: Standard Plan Review: too few permits to say (19)Edgewater: Standard Plan Review: half within 77 days

Standard Plan Review

90days for half the permits citywide, last 12 months

Longest waits:

Shortest waits:

Tap or hover any area, or choose one from the list. Areas with fewer than 20 permits on a path show as too few to say.

Community area outlines: City of Chicago, Boundaries - Community Areas. A permit counts in the community area of its primary address. Every number on the map is also in the table below.

Every community area

Community areaPermits issued, 12 monthsStandard Plan ReviewExpress Permit Program, half within (days)
PermitsHalf (days)8 in 10 (days)
Community areaPermitsStandard permitsStandard half (days)Standard 8 in 10 (days)Express half (days)
Near North Side2,389132721605
Loop2,3741386762
Near West Side1,583129541482
West Town1,2521771142003
Lake View1,170144671653
Lincoln Park1,021115881504
Austin8991041032093
Logan Square8081261192203
Auburn Gresham58561841543
Portage Park56750771591
Irving Park51680821552
Humboldt Park510109912052
Edgewater50455771663
Roseland494361201613
North Center49352811821
Lincoln Square47262781972
North Lawndale44693911905
South Shore44454892104
Uptown43957931664
Ashburn43617too fewtoo few2
Show the other 57 community areas
Community areaPermits issued, 12 monthsStandard Plan ReviewExpress Permit Program, half within (days)
PermitsHalf (days)8 in 10 (days)
Community areaPermitsStandard permitsStandard half (days)Standard 8 in 10 (days)Express half (days)
West Ridge43461842273
Washington Heights41623981613
New City413571211903
Garfield Ridge40128601351
O'Hare39719too fewtoo few0
Norwood Park38938731531
West Englewood388611192305
South Lawndale384651152453
Lower West Side366711012533
Belmont Cragin36538841621
Near South Side35864191362
Hyde Park35146511394
Greater Grand Crossing343461002123
West Pullman34328911633
Englewood340621081745
Chicago Lawn338341102742
Woodlawn32173781334
Chatham31829961854
Grand Boulevard311581061863
South Chicago306371052093
Morgan Park30533971642
Albany Park303441031613
Rogers Park29845851553
Avondale287491352623
East Garfield Park28168781663
Dunning268231302712
Bridgeport266451171894
Beverly260251151784
Forest Glen24331791601
Jefferson Park23630501381
Brighton Park22731982013
West Lawn22112too fewtoo few2
West Garfield Park20636862365
Kenwood191211061988
Gage Park19013too fewtoo few2
Avalon Park187211251673
Calumet Heights1877too fewtoo few1
Mount Greenwood16824581232
South Deering15910too fewtoo few3
McKinley Park158241182311
Clearing1559too fewtoo few3
North Park154221062001
Douglas13913too fewtoo few6
East Side1366too fewtoo few3
Hermosa13418too fewtoo few2
Washington Park13246911486
Pullman12916too fewtoo few3
Archer Heights11113too fewtoo few2
Edison Park10918too fewtoo few1
Montclare10810too fewtoo few5
Hegewisch872too fewtoo few2
West Elsdon8714too fewtoo few2
Armour Square7516too fewtoo few6
Fuller Park5511too fewtoo few4
Oakland453too fewtoo few3
Riverdale394too fewtoo fewtoo few
Burnside331too fewtoo few1

Last 12 months. Areas with fewer than 20 permits on a path show as too few. 296 permits had no community area on the record and count only in the city totals.

Download the numbers

Every figure on this page and its permit type pages, as one CSV file: citywide, by review path, permit type, community area and month.

Download the CSV

Planning a job around a permit?

The 8 in 10 figure for your permit type and path is how long most permits took to come through; the 9 in 10 figure shows how long the slow ones ran. For your own permit, check with the Department of Buildings.

City permit application guide

More free Chicago data

Trackers built from City records for trade owners: rat complaints by community area, demolition rodent baiting, trades news and more.

See every free tracker

How this page is made

The measure is the City's own processing time field on each issued permit: the number of days between the day the City began reviewing the application and the issue date. We do not estimate any wait.

Issued permits only. An application still in review has no issue date yet, so it is counted only once it is issued. When a review path slows down, these figures catch up as the slow permits come through.

Full method and checks

For most permit types, the City's issue date is the day it found the permit ready to issue, subject to paying the fee. For the Express Permit Program it is the day the permit was issued after the fee was paid. The days count every day in between, whoever was working on the application at the time.

Half within means half of the permits took that many days or fewer (the median). 8 in 10 within means at least 8 in 10 permits took that many days or fewer; 9 in 10 within is the same for 9 in 10. Each is the real day count of the permit at that spot in the line, not an average. Waits have a long tail: a few permits take far longer than most, which is why the page shows 8 in 10 and 9 in 10 beside half within.

Same-day permits: many Express Permit Program permits are issued the same day the City starts reviewing them, so they show 0 days. The share issued the same day is shown for each path.

A group with fewer than 20 permits shows its count but no day figures, because a median from a handful of permits says little. A permit type gets its own page when the City issued at least 300 of them in the last 12 months.

A permit counts in the community area of its primary address, as the City records it. Permits the City later voided or revoked are not in the dataset.

1 issued permit from Nov 1, 2024 to Nov 1, 2026 had no usable processing time and is left out.

Check: on 63,092 of 63,092 permits kept (100.0%), the processing time equals the days between the two dates on the record.

Questions

How long does a building permit take in Chicago?

It depends most on the review path. The tables on this page show, for permits the City issued in the last 12 months, how many days half of them took and how many days 8 in 10 took, by permit type and review path. For your own permit, check with the Department of Buildings.

Where do these numbers come from?

From the City of Chicago's Building Permits dataset. Each issued permit carries a processing time field, the number of days between the day the City began reviewing the application and the issue date. We count those days; we do not estimate them.

Why can a permit show zero days?

Many Express Permit Program permits are issued the same day the City starts reviewing them, so their processing time is 0. The page shows the share issued the same day for each review path.

Does this include permits still waiting for review?

No. Only issued permits have an issue date, so an application still in review is not counted until it is issued. When a review path slows down, its figures here catch up as those permits are issued.

How often is the page updated?

Once a week, on Monday mornings, from the City's records up to the day before the update. The City updates the dataset daily.

Find your permit typeDownload the CSV

More free Chicago data

All 14 free Chicago data pages