Chicago issued 1,121 elevator equipment permits in the 12 months to Nov 1, 2026. Half were issued the same day the City started review, and 8 in 10 within 5 days.
Figures as of Nov 1, 2026: issued from Nov 2, 2025 to Nov 1, 2026, from City of Chicago records pulled Nov 2, 2026. Updated weekly.
By review path
| Review path | Permits issued, 12 months | Half within (days) | 8 in 10 within (days) | 9 in 10 within (days) | Same day |
|---|---|---|---|---|---|
| Elevators and Other Conveyances | 1,121 | 0 | 5 | 7 | 74% |
Month by month
The last 24 complete months, by month issued.
Half were issued within (days)8 in 10 were issued within (days)
Half were issued within (days)8 in 10 were issued within (days)
Every month as a table
| Month issued | All review paths: half / 8 in 10 (days) | Elevators and Other Conveyances: half / 8 in 10 (days) |
|---|---|---|
| Oct 2026 | 0 / 2102 permits | 0 / 2102 permits |
| Sep 2026 | 0 / 097 permits | 0 / 097 permits |
| Aug 2026 | 0 / 5104 permits | 0 / 5104 permits |
| Jul 2026 | 0 / 5103 permits | 0 / 5103 permits |
| Jun 2026 | 0 / 589 permits | 0 / 589 permits |
| May 2026 | 0 / 5105 permits | 0 / 5105 permits |
| Apr 2026 | 0 / 082 permits | 0 / 082 permits |
| Mar 2026 | 0 / 269 permits | 0 / 269 permits |
| Feb 2026 | 0 / 599 permits | 0 / 599 permits |
| Jan 2026 | 0 / 071 permits | 0 / 071 permits |
| Dec 2025 | 0 / 6120 permits | 0 / 6120 permits |
| Nov 2025 | 0 / 780 permits | 0 / 780 permits |
| Oct 2025 | 0 / 798 permits | 0 / 798 permits |
| Sep 2025 | 0 / 592 permits | 0 / 592 permits |
| Aug 2025 | 0 / 789 permits | 0 / 789 permits |
| Jul 2025 | 0 / 089 permits | 0 / 089 permits |
| Jun 2025 | 0 / 569 permits | 0 / 569 permits |
| May 2025 | 0 / 189 permits | 0 / 189 permits |
| Apr 2025 | 0 / 574 permits | 0 / 574 permits |
| Mar 2025 | 0 / 5100 permits | 0 / 5100 permits |
| Feb 2025 | 0 / 486 permits | 0 / 486 permits |
| Jan 2025 | 0 / 2108 permits | 0 / 2108 permits |
| Dec 2024 | 0 / 568 permits | 0 / 568 permits |
| Nov 2024 | 0 / 082 permits | 0 / 082 permits |
Against a year earlier
| Review path | Aug to Oct 2026: half within (days) | Aug to Oct 2025: half within (days) | Change |
|---|---|---|---|
| All review paths | 0303 permits | 0279 permits | Same |
| Elevators and Other Conveyances | 0303 permits | 0279 permits | Same |
Every community area
| Community area | Permits issued, 12 months | Half within (days) | 8 in 10 within (days) | 9 in 10 within (days) |
|---|---|---|---|---|
| Near North Side | 227 | 0 | 7 | 8 |
| Loop | 175 | 0 | 6 | 7 |
| Near West Side | 109 | 0 | 0 | 6 |
| Lake View | 57 | 0 | 5 | 5 |
| West Town | 50 | 0 | 7 | 14 |
| Lincoln Park | 33 | 0 | 5 | 7 |
| Near South Side | 26 | 0 | 7 | 12 |
| Edgewater | 25 | 0 | 6 | 7 |
| Hyde Park | 22 | 0 | 2 | 5 |
| O'Hare | 19 | too few | too few | too few |
| Douglas | 18 | too few | too few | too few |
| Logan Square | 16 | too few | too few | too few |
| South Lawndale | 16 | too few | too few | too few |
| Austin | 15 | too few | too few | too few |
| Uptown | 15 | too few | too few | too few |
| Lincoln Square | 13 | too few | too few | too few |
| Belmont Cragin | 12 | too few | too few | too few |
| North Center | 12 | too few | too few | too few |
| Roseland | 11 | too few | too few | too few |
| Auburn Gresham | 9 | too few | too few | too few |
Show the other 50 community areas
| Community area | Permits issued, 12 months | Half within (days) | 8 in 10 within (days) | 9 in 10 within (days) |
|---|---|---|---|---|
| Bridgeport | 9 | too few | too few | too few |
| East Garfield Park | 9 | too few | too few | too few |
| Humboldt Park | 9 | too few | too few | too few |
| Irving Park | 9 | too few | too few | too few |
| New City | 9 | too few | too few | too few |
| Grand Boulevard | 8 | too few | too few | too few |
| Lower West Side | 8 | too few | too few | too few |
| Portage Park | 8 | too few | too few | too few |
| Rogers Park | 8 | too few | too few | too few |
| West Englewood | 8 | too few | too few | too few |
| Englewood | 7 | too few | too few | too few |
| Kenwood | 7 | too few | too few | too few |
| South Shore | 7 | too few | too few | too few |
| West Ridge | 7 | too few | too few | too few |
| Avondale | 6 | too few | too few | too few |
| Dunning | 6 | too few | too few | too few |
| Greater Grand Crossing | 6 | too few | too few | too few |
| Morgan Park | 6 | too few | too few | too few |
| South Chicago | 6 | too few | too few | too few |
| Washington Heights | 6 | too few | too few | too few |
| West Pullman | 6 | too few | too few | too few |
| Brighton Park | 5 | too few | too few | too few |
| East Side | 5 | too few | too few | too few |
| McKinley Park | 5 | too few | too few | too few |
| Norwood Park | 5 | too few | too few | too few |
| South Deering | 5 | too few | too few | too few |
| Woodlawn | 5 | too few | too few | too few |
| Albany Park | 4 | too few | too few | too few |
| Beverly | 4 | too few | too few | too few |
| Chicago Lawn | 4 | too few | too few | too few |
| Hermosa | 4 | too few | too few | too few |
| Oakland | 4 | too few | too few | too few |
| Armour Square | 3 | too few | too few | too few |
| North Lawndale | 3 | too few | too few | too few |
| North Park | 3 | too few | too few | too few |
| Washington Park | 3 | too few | too few | too few |
| West Garfield Park | 3 | too few | too few | too few |
| Avalon Park | 2 | too few | too few | too few |
| Chatham | 2 | too few | too few | too few |
| Forest Glen | 2 | too few | too few | too few |
| Montclare | 2 | too few | too few | too few |
| Mount Greenwood | 2 | too few | too few | too few |
| Pullman | 2 | too few | too few | too few |
| West Lawn | 2 | too few | too few | too few |
| Archer Heights | 1 | too few | too few | too few |
| Calumet Heights | 1 | too few | too few | too few |
| Clearing | 1 | too few | too few | too few |
| Gage Park | 1 | too few | too few | too few |
| Garfield Ridge | 1 | too few | too few | too few |
| Riverdale | 1 | too few | too few | too few |
Areas with fewer than 20 permits show as too few. 1 permit had no community area on the record and counts only in the totals. 7 community areas with no permits of this type in the last 12 months are left out.
How this page is made
The measure is the City's own processing time field on each issued permit: the number of days between the day the City began reviewing the application and the issue date. We do not estimate any wait.
Issued permits only. An application still in review has no issue date yet, so it is counted only once it is issued. When a review path slows down, these figures catch up as the slow permits come through.
Half within means half of the permits took that many days or fewer (the median). 8 in 10 within means at least 8 in 10 permits took that many days or fewer; 9 in 10 within is the same for 9 in 10. Each is the real day count of the permit at that spot in the line, not an average. Waits have a long tail: a few permits take far longer than most, which is why the page shows 8 in 10 and 9 in 10 beside half within.
The full method and a CSV of every figure are on the main permit wait times page.