Renovation and Alteration Permit Wait Times in Chicago
Chicago issued 5,305 renovation and alteration permits in the 12 months to Nov 1, 2026. Half were issued within 59 days of the City starting review, and 8 in 10 within 143 days.
Figures as of Nov 1, 2026: issued from Nov 2, 2025 to Nov 1, 2026, from City of Chicago records pulled Nov 2, 2026. Updated weekly.
By review path
| Review path | Permits issued, 12 months | Half within (days) | 8 in 10 within (days) | 9 in 10 within (days) | Same day |
|---|---|---|---|---|---|
| Standard Plan Review | 2,632 | 104 | 189 | 276 | 0% |
| Self Certification | 2,467 | 27 | 63 | 102 | 1% |
| Direct Developer Services | 203 | 102 | 188 | 290 | 0% |
| Traditional Developer Services | 3 | too few | too few | too few | too few |
Month by month
The last 24 complete months, by month issued.
Half were issued within (days)8 in 10 were issued within (days)
Half were issued within (days)8 in 10 were issued within (days)
Half were issued within (days)8 in 10 were issued within (days)
Half were issued within (days)8 in 10 were issued within (days)
Every month as a table
| Month issued | All review paths: half / 8 in 10 (days) | Standard Plan Review: half / 8 in 10 (days) | Self Certification: half / 8 in 10 (days) | Direct Developer Services: half / 8 in 10 (days) |
|---|---|---|---|---|
| Oct 2026 | 67 / 165441 permits | 113 / 214223 permits | 31 / 74207 permits | too few(11 permits) |
| Sep 2026 | 51 / 138482 permits | 97 / 179229 permits | 27 / 55234 permits | too few(19 permits) |
| Aug 2026 | 66 / 142497 permits | 107 / 175231 permits | 34 / 77232 permits | 108 / 16834 permits |
| Jul 2026 | 64 / 155496 permits | 115 / 206235 permits | 37 / 69235 permits | 116 / 62326 permits |
| Jun 2026 | 63 / 141427 permits | 112 / 211205 permits | 26 / 63207 permits | too few(15 permits) |
| May 2026 | 53 / 135474 permits | 84 / 193253 permits | 27 / 62204 permits | too few(16 permits) |
| Apr 2026 | 52 / 140519 permits | 89 / 172258 permits | 27 / 56243 permits | too few(17 permits) |
| Mar 2026 | 58 / 158445 permits | 114 / 203202 permits | 23 / 62229 permits | too few(14 permits) |
| Feb 2026 | 63 / 148372 permits | 105 / 194187 permits | 24 / 70174 permits | too few(10 permits) |
| Jan 2026 | 65 / 136406 permits | 106 / 189214 permits | 24 / 60179 permits | too few(13 permits) |
| Dec 2025 | 58 / 140374 permits | 97 / 189202 permits | 19 / 59154 permits | too few(18 permits) |
| Nov 2025 | 53 / 134372 permits | 93 / 187193 permits | 22 / 53169 permits | too few(10 permits) |
| Oct 2025 | 50 / 127504 permits | 95 / 167237 permits | 27 / 71257 permits | too few(10 permits) |
| Sep 2025 | 55 / 121521 permits | 90 / 164263 permits | 28 / 64242 permits | too few(15 permits) |
| Aug 2025 | 63 / 134441 permits | 93 / 192234 permits | 41 / 76189 permits | too few(17 permits) |
| Jul 2025 | 56 / 127518 permits | 85 / 175272 permits | 28 / 57228 permits | too few(18 permits) |
| Jun 2025 | 48 / 128488 permits | 84 / 176245 permits | 31 / 59232 permits | too few(10 permits) |
| May 2025 | 57 / 122480 permits | 84 / 188264 permits | 24 / 64201 permits | too few(13 permits) |
| Apr 2025 | 51 / 130544 permits | 78 / 171282 permits | 25 / 68248 permits | too few(13 permits) |
| Mar 2025 | 47 / 141436 permits | 90 / 182212 permits | 21 / 59207 permits | too few(16 permits) |
| Feb 2025 | 55 / 140362 permits | 84 / 211205 permits | 21 / 57142 permits | too few(15 permits) |
| Jan 2025 | 43 / 122465 permits | 73 / 161236 permits | 22 / 63222 permits | too few(7 permits) |
| Dec 2024 | 45 / 120414 permits | 77 / 191206 permits | 25 / 57193 permits | too few(15 permits) |
| Nov 2024 | 49 / 128428 permits | 64 / 164247 permits | 33 / 70169 permits | too few(12 permits) |
Against a year earlier
| Review path | Aug to Oct 2026: half within (days) | Aug to Oct 2025: half within (days) | Change |
|---|---|---|---|
| All review paths | 621,420 permits | 581,466 permits | 4 days longer |
| Standard Plan Review | 106683 permits | 93734 permits | 13 days longer |
| Self Certification | 30673 permits | 31688 permits | 1 day shorter |
| Direct Developer Services | 10364 permits | 8542 permits | 18 days longer |
Every community area
| Community area | Permits issued, 12 months | Half within (days) | 8 in 10 within (days) | 9 in 10 within (days) |
|---|---|---|---|---|
| Loop | 499 | 11 | 37 | 72 |
| Near North Side | 419 | 30 | 77 | 139 |
| Near West Side | 315 | 29 | 98 | 158 |
| West Town | 242 | 81 | 178 | 266 |
| Lake View | 213 | 56 | 144 | 224 |
| Lincoln Park | 193 | 67 | 134 | 211 |
| Logan Square | 191 | 85 | 172 | 236 |
| Austin | 143 | 70 | 161 | 227 |
| Humboldt Park | 121 | 72 | 160 | 236 |
| Lincoln Square | 106 | 61 | 135 | 207 |
| Irving Park | 102 | 61 | 147 | 250 |
| Auburn Gresham | 96 | 84 | 147 | 201 |
| North Center | 96 | 57 | 126 | 169 |
| South Lawndale | 91 | 74 | 174 | 267 |
| Portage Park | 89 | 53 | 134 | 159 |
| Edgewater | 87 | 52 | 106 | 200 |
| West Englewood | 87 | 101 | 221 | 315 |
| Englewood | 84 | 90 | 170 | 279 |
| North Lawndale | 81 | 89 | 180 | 261 |
| Hyde Park | 75 | 37 | 85 | 148 |
Show the other 56 community areas
| Community area | Permits issued, 12 months | Half within (days) | 8 in 10 within (days) | 9 in 10 within (days) |
|---|---|---|---|---|
| Lower West Side | 75 | 82 | 227 | 360 |
| New City | 73 | 105 | 190 | 276 |
| Uptown | 71 | 74 | 138 | 187 |
| Avondale | 69 | 65 | 171 | 275 |
| Woodlawn | 69 | 56 | 133 | 227 |
| South Shore | 68 | 84 | 209 | 316 |
| Greater Grand Crossing | 66 | 71 | 178 | 234 |
| West Ridge | 66 | 84 | 174 | 261 |
| Roseland | 60 | 76 | 152 | 162 |
| Albany Park | 55 | 68 | 139 | 192 |
| Near South Side | 52 | 72 | 160 | 191 |
| Norwood Park | 52 | 62 | 140 | 217 |
| Rogers Park | 52 | 74 | 141 | 160 |
| Bridgeport | 49 | 70 | 179 | 196 |
| South Chicago | 48 | 79 | 180 | 301 |
| Chatham | 47 | 56 | 148 | 332 |
| East Garfield Park | 47 | 83 | 189 | 276 |
| Kenwood | 45 | 94 | 165 | 172 |
| O'Hare | 45 | 9 | 105 | 159 |
| Belmont Cragin | 44 | 77 | 159 | 208 |
| Forest Glen | 44 | 71 | 164 | 252 |
| Grand Boulevard | 43 | 112 | 238 | 408 |
| West Garfield Park | 41 | 79 | 160 | 246 |
| Chicago Lawn | 40 | 81 | 189 | 304 |
| Brighton Park | 37 | 98 | 217 | 287 |
| Garfield Ridge | 36 | 58 | 113 | 185 |
| Jefferson Park | 35 | 55 | 138 | 239 |
| West Pullman | 34 | 84 | 172 | 332 |
| Beverly | 33 | 100 | 178 | 281 |
| Morgan Park | 29 | 79 | 140 | 348 |
| Dunning | 28 | 74 | 197 | 373 |
| Edison Park | 28 | 79 | 134 | 273 |
| Avalon Park | 26 | 76 | 147 | 200 |
| North Park | 26 | 77 | 140 | 252 |
| Washington Heights | 25 | 95 | 143 | 336 |
| Ashburn | 24 | 72 | 178 | 233 |
| McKinley Park | 24 | 81 | 206 | 291 |
| Hermosa | 23 | 97 | 217 | 236 |
| Mount Greenwood | 23 | 78 | 166 | 237 |
| Gage Park | 22 | 61 | 162 | 177 |
| Washington Park | 21 | 140 | 265 | 290 |
| Archer Heights | 20 | 53 | 118 | 338 |
| Douglas | 17 | too few | too few | too few |
| Fuller Park | 15 | too few | too few | too few |
| West Elsdon | 15 | too few | too few | too few |
| Pullman | 14 | too few | too few | too few |
| West Lawn | 14 | too few | too few | too few |
| Calumet Heights | 12 | too few | too few | too few |
| Clearing | 12 | too few | too few | too few |
| East Side | 12 | too few | too few | too few |
| South Deering | 12 | too few | too few | too few |
| Montclare | 10 | too few | too few | too few |
| Armour Square | 9 | too few | too few | too few |
| Hegewisch | 7 | too few | too few | too few |
| Oakland | 6 | too few | too few | too few |
| Riverdale | 3 | too few | too few | too few |
Areas with fewer than 20 permits show as too few. 2 permits had no community area on the record and count only in the totals. 1 community area with no permits of this type in the last 12 months is left out.
How this page is made
The measure is the City's own processing time field on each issued permit: the number of days between the day the City began reviewing the application and the issue date. We do not estimate any wait.
Issued permits only. An application still in review has no issue date yet, so it is counted only once it is issued. When a review path slows down, these figures catch up as the slow permits come through.
Half within means half of the permits took that many days or fewer (the median). 8 in 10 within means at least 8 in 10 permits took that many days or fewer; 9 in 10 within is the same for 9 in 10. Each is the real day count of the permit at that spot in the line, not an average. Waits have a long tail: a few permits take far longer than most, which is why the page shows 8 in 10 and 9 in 10 beside half within.
The full method and a CSV of every figure are on the main permit wait times page.