New Construction Permit Wait Times in Chicago
Chicago issued 1,559 new construction permits in the 12 months to Nov 1, 2026. Half were issued within 55 days of the City starting review, and 8 in 10 within 138 days.
Figures as of Nov 1, 2026: issued from Nov 2, 2025 to Nov 1, 2026, from City of Chicago records pulled Nov 2, 2026. Updated weekly.
By review path
| Review path | Permits issued, 12 months | Half within (days) | 8 in 10 within (days) | 9 in 10 within (days) | Same day |
|---|---|---|---|---|---|
| Standard Plan Review | 912 | 43 | 137 | 207 | 5% |
| Self Certification | 528 | 56 | 112 | 168 | 0% |
| Direct Developer Services | 118 | 135 | 224 | 502 | 0% |
| Traditional Developer Services | 1 | too few | too few | too few | too few |
Month by month
The last 24 complete months, by month issued.
Half were issued within (days)8 in 10 were issued within (days)
Half were issued within (days)8 in 10 were issued within (days)
Half were issued within (days)8 in 10 were issued within (days)
Every month as a table
| Month issued | All review paths: half / 8 in 10 (days) | Standard Plan Review: half / 8 in 10 (days) | Self Certification: half / 8 in 10 (days) | Direct Developer Services: half / 8 in 10 (days) |
|---|---|---|---|---|
| Oct 2026 | 60 / 170165 permits | 50 / 16898 permits | 56 / 15358 permits | too few(9 permits) |
| Sep 2026 | 42 / 94157 permits | 6 / 7692 permits | 54 / 9255 permits | too few(10 permits) |
| Aug 2026 | 49 / 132169 permits | 22 / 132106 permits | 57 / 10949 permits | too few(14 permits) |
| Jul 2026 | 45 / 127186 permits | 12 / 91121 permits | 61 / 11355 permits | too few(10 permits) |
| Jun 2026 | 32 / 103129 permits | 9 / 6792 permits | 51 / 11428 permits | too few(9 permits) |
| May 2026 | 35 / 89130 permits | 7 / 7081 permits | 47 / 12241 permits | too few(8 permits) |
| Apr 2026 | 48 / 126157 permits | 42 / 11782 permits | 48 / 10462 permits | too few(12 permits) |
| Mar 2026 | 68 / 198132 permits | 90 / 23170 permits | 42 / 8951 permits | too few(11 permits) |
| Feb 2026 | 63 / 12982 permits | 57 / 12949 permits | 70 / 13827 permits | too few(6 permits) |
| Jan 2026 | 109 / 22468 permits | 127 / 22433 permits | 69 / 11821 permits | too few(14 permits) |
| Dec 2025 | 91 / 17490 permits | 91 / 20448 permits | 84 / 14635 permits | too few(7 permits) |
| Nov 2025 | 67 / 14794 permits | 67 / 16340 permits | 55 / 7446 permits | too few(8 permits) |
| Oct 2025 | 56 / 164133 permits | 12 / 16071 permits | 51 / 14248 permits | too few(14 permits) |
| Sep 2025 | 52 / 129142 permits | 7 / 8979 permits | 58 / 9246 permits | too few(17 permits) |
| Aug 2025 | 51 / 126175 permits | 13 / 90105 permits | 70 / 13954 permits | too few(16 permits) |
| Jul 2025 | 30 / 107160 permits | 7 / 86109 permits | 54 / 10140 permits | too few(11 permits) |
| Jun 2025 | 90 / 151161 permits | 13 / 7871 permits | 143 / 16083 permits | too few(7 permits) |
| May 2025 | 49 / 157131 permits | 15 / 9383 permits | 63 / 13734 permits | too few(14 permits) |
| Apr 2025 | 35 / 123124 permits | 12 / 5356 permits | 48 / 13058 permits | too few(10 permits) |
| Mar 2025 | 83 / 30695 permits | 78 / 28240 permits | 76 / 46146 permits | too few(9 permits) |
| Feb 2025 | 61 / 14880 permits | 68 / 13545 permits | 28 / 8425 permits | too few(10 permits) |
| Jan 2025 | 69 / 13175 permits | 64 / 13144 permits | 70 / 11925 permits | too few(5 permits) |
| Dec 2024 | 63 / 11976 permits | 71 / 21931 permits | 45 / 9038 permits | too few(7 permits) |
| Nov 2024 | 75 / 19982 permits | 75 / 19940 permits | 57 / 17330 permits | too few(12 permits) |
Against a year earlier
| Review path | Aug to Oct 2026: half within (days) | Aug to Oct 2025: half within (days) | Change |
|---|---|---|---|
| All review paths | 49491 permits | 52450 permits | 3 days shorter |
| Standard Plan Review | 24296 permits | 11255 permits | 13 days longer |
| Self Certification | 56162 permits | 63148 permits | 7 days shorter |
| Direct Developer Services | 12433 permits | 13347 permits | 9 days shorter |
Every community area
| Community area | Permits issued, 12 months | Half within (days) | 8 in 10 within (days) | 9 in 10 within (days) |
|---|---|---|---|---|
| Near West Side | 103 | 37 | 116 | 199 |
| Loop | 102 | 3 | 8 | 16 |
| West Town | 97 | 75 | 185 | 250 |
| Lake View | 92 | 42 | 109 | 170 |
| Lincoln Park | 74 | 37 | 113 | 158 |
| North Lawndale | 65 | 69 | 100 | 137 |
| East Garfield Park | 62 | 63 | 113 | 224 |
| North Center | 62 | 54 | 125 | 182 |
| Near North Side | 61 | 6 | 104 | 182 |
| Logan Square | 57 | 68 | 146 | 298 |
| Humboldt Park | 51 | 69 | 190 | 252 |
| Near South Side | 48 | 7 | 36 | 84 |
| Grand Boulevard | 44 | 71 | 112 | 126 |
| Lower West Side | 40 | 72 | 155 | 268 |
| Woodlawn | 37 | 55 | 124 | 160 |
| Washington Park | 36 | 71 | 128 | 182 |
| Austin | 32 | 87 | 195 | 300 |
| Lincoln Square | 30 | 63 | 146 | 207 |
| Uptown | 25 | 99 | 189 | 305 |
| Irving Park | 24 | 66 | 110 | 128 |
Show the other 53 community areas
| Community area | Permits issued, 12 months | Half within (days) | 8 in 10 within (days) | 9 in 10 within (days) |
|---|---|---|---|---|
| Edgewater | 23 | 58 | 126 | 168 |
| West Ridge | 22 | 43 | 111 | 330 |
| Morgan Park | 20 | 91 | 157 | 164 |
| Armour Square | 19 | too few | too few | too few |
| Bridgeport | 18 | too few | too few | too few |
| New City | 18 | too few | too few | too few |
| Avondale | 17 | too few | too few | too few |
| Hyde Park | 16 | too few | too few | too few |
| Albany Park | 15 | too few | too few | too few |
| Brighton Park | 15 | too few | too few | too few |
| Norwood Park | 14 | too few | too few | too few |
| South Lawndale | 14 | too few | too few | too few |
| Douglas | 12 | too few | too few | too few |
| Jefferson Park | 12 | too few | too few | too few |
| McKinley Park | 12 | too few | too few | too few |
| Rogers Park | 12 | too few | too few | too few |
| Portage Park | 11 | too few | too few | too few |
| West Pullman | 9 | too few | too few | too few |
| Garfield Ridge | 8 | too few | too few | too few |
| O'Hare | 8 | too few | too few | too few |
| Edison Park | 7 | too few | too few | too few |
| Forest Glen | 7 | too few | too few | too few |
| West Garfield Park | 7 | too few | too few | too few |
| Chicago Lawn | 6 | too few | too few | too few |
| Dunning | 6 | too few | too few | too few |
| Mount Greenwood | 6 | too few | too few | too few |
| South Chicago | 6 | too few | too few | too few |
| West Englewood | 6 | too few | too few | too few |
| Auburn Gresham | 5 | too few | too few | too few |
| North Park | 5 | too few | too few | too few |
| South Shore | 5 | too few | too few | too few |
| Belmont Cragin | 4 | too few | too few | too few |
| Englewood | 4 | too few | too few | too few |
| Gage Park | 4 | too few | too few | too few |
| Kenwood | 4 | too few | too few | too few |
| Pullman | 4 | too few | too few | too few |
| South Deering | 4 | too few | too few | too few |
| Washington Heights | 4 | too few | too few | too few |
| Archer Heights | 3 | too few | too few | too few |
| Greater Grand Crossing | 3 | too few | too few | too few |
| Hermosa | 3 | too few | too few | too few |
| Roseland | 3 | too few | too few | too few |
| Ashburn | 2 | too few | too few | too few |
| Beverly | 2 | too few | too few | too few |
| Burnside | 2 | too few | too few | too few |
| Montclare | 2 | too few | too few | too few |
| West Lawn | 2 | too few | too few | too few |
| Avalon Park | 1 | too few | too few | too few |
| Chatham | 1 | too few | too few | too few |
| Clearing | 1 | too few | too few | too few |
| Fuller Park | 1 | too few | too few | too few |
| Oakland | 1 | too few | too few | too few |
| Riverdale | 1 | too few | too few | too few |
Areas with fewer than 20 permits show as too few. 4 community areas with no permits of this type in the last 12 months are left out.
How this page is made
The measure is the City's own processing time field on each issued permit: the number of days between the day the City began reviewing the application and the issue date. We do not estimate any wait.
Issued permits only. An application still in review has no issue date yet, so it is counted only once it is issued. When a review path slows down, these figures catch up as the slow permits come through.
Half within means half of the permits took that many days or fewer (the median). 8 in 10 within means at least 8 in 10 permits took that many days or fewer; 9 in 10 within is the same for 9 in 10. Each is the real day count of the permit at that spot in the line, not an average. Waits have a long tail: a few permits take far longer than most, which is why the page shows 8 in 10 and 9 in 10 beside half within.
The full method and a CSV of every figure are on the main permit wait times page.