ProofNotFluff

Free calculator, 2026 CDOT fees

Chicago Public Way Permit Cost Calculator

Pick what you are putting in the street, alley or sidewalk and get an estimate of the CDOT fees from the City's 2026 Permit Fee Schedule, with each line of the math shown.

Fees from CDOT's 2026 Permit Fee Schedule, effective January 1, 2026Open the City's fee schedule (PDF)Fees can change; confirm with CDOT.

Price your permit

What are you pricing?
Dumpster in the public way
Work vehicle, equipment or barricade
ft
Sidewalk or street closure for building work
ft
Opening or cut in the public way
ft
Estimated CDOT fees
$0.00
From the 2026 fee schedule

    Fees can change; confirm with CDOT before you apply.

    The 2026 fees this calculator uses

    Typed from CDOT's 2026 Permit Fee Schedule, with the schedule's own page numbers. CBD is the Central Business District.

    Dumpster permits: application fee (page 2)

    Residential and arterial streets are outside the CBD.

    ClosureCBDResidentialArterial
    Full closure$92.63$22.60$56.51
    Partial closure$92.63$22.60$56.51

    Dumpster placement usage fee (page 2)

    The same for alley, curb lane, parkway and sidewalk.

    Size and location1 to 3 daysPer month
    Class A (30 cubic yards or less), outside the CBD$50.00$100.00
    Class A (30 cubic yards or less), inside the CBD$100.00$200.00
    Class B (more than 30 cubic yards), outside the CBD$100.00$200.00
    Class B (more than 30 cubic yards), inside the CBD$200.00$400.00

    Occupy the public right of way: application fee (page 6)

    The schedule applies it to work vehicles, temporary driveways, barricades and operating equipment. Residential and arterial streets are outside the CBD.

    ClosureCBDResidentialArterial
    Full closure$316.49$158.25$158.25
    Partial closure$22.60$22.60$22.60

    Vehicles, equipment and other items (page 7)

    Names as the City's schedule prints them.

    Show the 25 items the calculator prices
    ItemOutside CBDInside CBD
    Parking vehicles: Parking Moving Van$30.00 per day per vehicle$60.00 per day per vehicle
    Parking vehicles: Citywide (Annual)$600.00 per vehicle$600.00 per vehicle
    Parking vehicles: Residential (Annual)$100.00 per vehicle$100.00 per vehicle
    Parking vehicles: Work Vehicle Daily-Alley$30.00 per day per vehicle$60.00 per day per vehicle
    Parking vehicles: Work Vehicle Daily-Curb Lane$30.00 per day per vehicle$60.00 per day per vehicle
    Parking vehicles: Work Vehicle Daily-Curb/Traffic Lane$30.00 per day per vehicle$60.00 per day per vehicle
    Parking vehicles: Work Vehicle Daily-Traffic Lane$30.00 per day per vehicle$60.00 per day per vehicle
    Parking vehicles: Work Vehicle - Alley (if a lane of at least 10 feet is left unobstructed)$6.00 per foot$12.00 per foot
    Parking vehicles: Work Vehicle - Alley (if a lane of at least 10 feet is not left unobstructed)$12.00 per foot$24.00 per foot
    Parking vehicles: Work Vehicle - Bicycle Lane$5.00 per foot$10.00 per foot
    Parking vehicles: Work Vehicle - Curb Lane$12.00 per foot$24.00 per foot
    Parking vehicles: Work Vehicle - Traffic Lane$24.00 per foot$48.00 per foot
    Parking vehicles: Work Vehicle - Sidewalk or parkway partial closure$2.50 per foot$5.00 per foot
    Parking vehicles: Work Vehicle - Sidewalk or parkway total closure$5.00 per foot$10.00 per foot
    Parking vehicles: Parking / Various Locations (Monthly)$20.00 per vehicle$100.00 per vehicle
    Parking vehicles: Parking / Various Locations (Semi-Annual)$100.00 per vehicle$500.00 per vehicle
    Operating equipment: Alley (if a lane of at least 10 feet is left unobstructed)$3.00 per foot$6.00 per foot
    Operating equipment: Alley (if a lane of at least 10 feet is not left unobstructed)$6.00 per foot$12.00 per foot
    Operating equipment: Bicycle Lane$2.50 per foot$5.00 per foot
    Operating equipment: Curb Lane$6.00 per foot$12.00 per foot
    Operating equipment: Sidewalk or parkway partial closure$1.25 per foot$2.50 per foot
    Operating equipment: Sidewalk or parkway total closure$2.50 per foot$5.00 per foot
    Operating equipment: Traffic Lane$12.00 per foot$24.00 per foot
    Other: Barricade - Sidewalk or parkway closure$2.50 per foot per month$5.00 per foot per month
    Other: Temporary Driveway$100.00 per month for every 25 feet$100.00 per month for every 25 feet

    Monthly usage fees for Types I, II and III (pages 8 and 9)

    Amounts for the CBD; outside the CBD the fees are one-half. Columns are days in place: 1 to 3 days is for all three types, the next five for Types I and III, the last two for Type II. The schedule says these fees are subject to a yearly CPI increase of up to 2.5%.

    Show all 7 placements
    Placement1 to 3 days4 to 180181 to 360361 to 540541 to 720721 or moreType II, 4 to 540Type II, 541 or more
    Sidewalk or parkway - partial closure: per foot$2.50$5.00$10.00$14.00$19.00C$5.00$10.00
    Sidewalk or parkway - partial closure: minimum a month$48.00$96.00$192.00$288.00$384.00$384.00$96.00$192.00
    Sidewalk or parkway - total closure: per foot$5.00$10.00$19.00$29.00$38.00D$10.00$19.00
    Sidewalk or parkway - total closure: minimum a month$96.00$192.00$384.00$576.00$768.00$768.00$192.00$384.00
    Bicycle lane - total closure: per foot$5.00$10.00$19.00$29.00$38.00$38.00$10.00$19.00
    Bicycle lane - total closure: minimum a month$96.00$192.00$384.00$576.00$768.00$768.00$192.00$384.00
    Street lane containing parking spaces: per foot$12.00$24.00$48.00$72.00$96.00$96.00$24.00$48.00
    Street lane containing parking spaces: minimum a month$240.00$480.00$960.00$1,440.00$1,920.00$1,920.00$480.00$960.00
    Street lane normally used for vehicular traffic, including a bus lane: per foot$24.00$48.00$96.00$144.00$192.00$192.00$48.00$96.00
    Street lane normally used for vehicular traffic, including a bus lane: minimum a month$480.00$960.00$1,920.00$2,880.00$3,840.00$3,840.00$960.00$1,920.00
    Alley - if a lane of at least 10 feet is left unobstructed: per foot$6.00$12.00$24.00$36.00$48.00$48.00$12.00$24.00
    Alley - if a lane of at least 10 feet is left unobstructed: minimum a month$120.00$240.00$480.00$720.00$960.00$960.00$240.00$480.00
    Alley - if a lane of at least 10 feet is not left unobstructed: per foot$12.00$24.00$48.00$72.00$96.00$96.00$24.00$48.00
    Alley - if a lane of at least 10 feet is not left unobstructed: minimum a month$240.00$480.00$960.00$1,440.00$1,920.00$1,920.00$480.00$960.00

    Swipe sideways for all eight columns.

    C: the previous monthly fee plus $4.00 times the length. D: the previous monthly fee plus $8.00 times the length.

    Openings in the public way (page 2)

    Fees double, and a degradation fee is added, on moratorium streets.

    PlacementFee
    ADA Ramp installation$389.26 per opening
    Street / Alley$778.54 per opening
    Sidewalk$778.54 per opening
    Parkway$389.26 per opening
    Soil Borings - Street$778.54 per opening
    Soil Borings - Parkway$389.26 per block
    Well Monitoring$778.54 per opening

    Degradation fee on moratorium streets (page 11)

    Fee = P times (length divided by 200) times $1,000.00, where P is the multiplier for the pavement's age in the table below. For a cut the length is set to 200 feet; for a trench the schedule says a minimum of 200 foot increments, which we read as at least 200 feet, prorated above that. The schedule says residential homeowners are exempt on repairs to existing sewer and water services. Moratorium streets are on CDOT's ChiStreetWork map.

    Age of the pavementMultiplier (P)
    More than 0 to 6 months20
    More than 6 and up to 12 months15
    More than 12 and up to 18 months10
    More than 18 and up to 24 months5
    More than 24 months, up to 5 years2.5

    How the calculator reads the schedule

    Every amount comes from CDOT's 2026 Permit Fee Schedule, effective January 1, 2026. The tables it uses are on this page, with the schedule's page numbers, and the calculator only adds and multiplies them.

    How each permit type is priced

    Dumpsters: the application fee depends on the street (CBD, or a residential or arterial street outside it), and the usage fee on the size class, inside or outside the CBD, for 1 to 3 days or per month. The schedule gives no rate between 3 days and a month, so the calculator asks you to pick one.

    Sidewalk and street closures: the schedule issues these permits in 30-day increments and sets a per-foot rate and a minimum monthly fee that both rise the longer the closure stays. Our reading: each 30-day block is charged at the rate for the days it falls in (days 181 to 210 at the 181 to 360 day rate, for example), as the per-foot rate times the length or the monthly minimum, whichever is more, then halved outside the CBD. CDOT may instead price the whole permit at one rate. Past 720 days, the schedule sets sidewalk and parkway closures at the previous monthly fee plus $4.00 or $8.00 times the length; we read this as adding again each month. Ask CDOT how it prices yours.

    Openings on a moratorium street: the opening fee doubles and the degradation fee from page 11 is added, using the schedule's own formula and multipliers. We show it for each cut, and charge a trench on at least 200 feet; both are our reading.

    Some items in the schedule are priced per foot without a time period, and some charges, like metered spaces your closure makes unusable, have no amount in that part of the schedule. The calculator says so where it applies. CDOT sets the fee on each permit.

    Where are dumpster permits going?

    See how many dumpster permits CDOT issued in each community area in the last 90 days, against a year ago, updated daily.

    See dumpster permits by neighborhood

    Questions

    How much is a dumpster permit in Chicago in 2026?

    Outside the Central Business District, a Class A dumpster (30 cubic yards or less) is $50.00 for 1 to 3 days or $100.00 a month, plus an application fee of $22.60 on a residential street or $56.51 on an arterial street. Inside the CBD the usage fees double and the application fee is $92.63.

    Does the size of the dumpster change the fee?

    Yes. Class B dumpsters, more than 30 cubic yards, cost twice Class A: $100.00 for 1 to 3 days or $200.00 a month outside the CBD, and $200.00 or $400.00 inside it.

    What is the Central Business District?

    It is the district whose boundaries the schedule points to in Municipal Code section 9-4-010. Many CDOT fees are higher there, and the schedule says closure fees outside it are one-half of the CBD amounts.

    What does a moratorium street add to an opening permit?

    The schedule says opening fees double on a moratorium street, which includes streets paved less than five years ago, and a degradation fee is added that is higher the newer the pavement. Its own example: one cut in a street paved 6 months ago carries a $20,000 degradation fee. The schedule says CDOT approves openings on these streets case by case.

    Will these fees change?

    CDOT says permit fees may change year to year. The schedule says opening fees rise 5% a year, and several other fees can rise with the Consumer Price Index. Confirm the fee with CDOT before you apply.

    More free Chicago data

    All 14 free Chicago data pages